A point-of-use transfer switch installs with two source feeds and one output, and no special conduit. This page covers what to check first, the usual sequence and the tests to run before you hand it over. The operating manual for your model governs the details.
Before you start
- Confirm the two sources are independent. Two circuits from the same panel protect against very little. Feed the switch from different PDUs or panels, ideally from different UPS systems.
- Confirm voltage, frequency and pole count against the nameplate, and that the rating covers the load with margin.
- Size each feeder breaker and its conductors to your electrical code and the operating manual for the model.
- Check that the available fault current at the installation point does not exceed the fault rating on the nameplate.
- Allow rack space and airflow: 1U for the DCC-I, 2U for the DCC-4-R, 4U for the DCC-II, DCC-III and DCC-4-R4. Use a rack shelf and cable strain relief where a unit’s weight exceeds the two-post mounting capacity of the rack.
Typical connection
Fail the preferred feed to see what the installed switch does.
Installation sequence
- Mount the unitRack-mount models fit a standard 19-inch rack. Wall-mount cabinets need a surface rated for the weight, with clearance for the door and the bypass handle.
- Connect the groundConnect the equipment grounding conductor to the switch's ground terminal first, before any source or output wiring.
- Connect source 1 and source 2Land each source on its own input. Keep A and B cabling separated and labelled from the breaker to the switch.
- Connect the outputFeed the rack power strip, the load panel or the equipment directly. Moving the equipment later means moving the switch with it, and nothing else.
- NeutralThe switch transfers the neutral with the phases on 2-pole and 4-pole models. Do not bond the two source neutrals together anywhere downstream.
- Connect monitoringWire the alarm contacts to your BMS, DCIM or RTU, and RS-485 where it is used.
- Energize and verifyClose source 1, then source 2. Both "available" indicators should light. Select the preferred source.
- Test the transferWith the load connected, open the preferred source breaker. The load should stay up, the indicators should show the alternate source, and the alarm should reach your monitoring system. Restore the source and confirm the retransfer.
- Test the bypass and documentWalk through the bypass sequence in the manual once while everyone is watching. Update the one-line diagram and label the rack.
General guidance only. Installation must be carried out by qualified personnel, to the operating manual and your local electrical code.
Questions engineers ask
Can I install the switch without shutting down the rack?
If the equipment is single-corded, connecting it to the switch means one planned interruption. After that, the bypass lets you service the switch without another.
Do the two sources need to be synchronized?
No. TwinSource switches transfer at any phase angle.
What breaker should feed the switch?
Size it, and its conductors, to your electrical code and the operating manual for the model. TwinSource ratings are 100% continuous; the sizing guide shows how to find the load current.
Put it to work
Narrow the range to your voltage, current and mounting, or send us your one-line diagram and talk to an engineer.